Trane and GWCCA Unveil Convention Center Upgrades Expected to Reduce Energy Use by More Than a Third

Atlanta, Feb. 29, 2017 – Leaders from Trane, a leading global provider of indoor comfort solutions and services and a brand of Ingersoll Rand, and the Georgia World Congress Center Authority (GWCCA) unveiled upgrades to the Atlanta convention center this week which are expected to cut energy costs and reduce the centers carbon footprint by 39 percent annually, saving more than $2.5 million in the first year alone.

“The upgrades and the benefits gained in the convention center puts us at the forefront in the hospitality industry for sustainability, and solidifies our place as the number one convention, sports and entertainment destination in the world,” said Kevin Duvall, chief operating officer at the GWCCA, and executive-in-charge of this project.

“These upgrades enable the GWCCA provide a more efficient, sustainable and comfortable convention center environment for staff and visitors,” said Cameron Griffith, solutions advisor for Trane. “Even better, that they are already significantly cutting energy costs.”

The GWCCA, featuring the landmark convention center, represents a significant economic driver for the state. GWCCA leaders report that the 2016 economic impact of the convention center was $1.1 billion and that in its entirety, the GWCCA, including the convention center, currently ranks as the number one sports, entertainment, and convention destination in the world.

Convention center upgrades were needed to improve lighting, increase the reliability and performance of heating and cooling solutions, and reduce the center’s carbon footprint to reflect the Authority’s commitment to environmental stewardship.

Performance Contracting Funded the Upgrades
The GWCCA funded the $28 million project through the Georgia Energy Savings Contracting Procurement program, making it the state’s largest stand-alone energy performance contract and the nation’s largest for any public assembly venue, according to the GWCCA.

Trane and GWCCA Unveil Convention Center Upgrades Expected to Reduce Energy Use by More Than a Third – 2

The performance contract allowed GWCCA to use future energy and operational savings to finance the infrastructure improvements up front. Performance contracting is a project delivery method that provides measurable business results to support strategic business objectives with reduced or eliminated capital funding requirements.

GWCCA leaders selected Trane through a competitive bid process to help enhance the convention center’s position as a sought-after location for major Atlanta-area events.

With 3.9 million square feet under one roof, the convention center operates much like a small city and needed to maintain operations during the upgrade process. Trane worked with the GWCC facilities team to develop a plan to address major business needs for the organization. Before identifying specific energy conservation measures, Trane and the GWCCA facilities team conducted an in-depth audit to identify opportunities for improvement.

Upgrades Included New Central Plant, Energy Management and Lighting
Based on the results of the audit, the facilities team selected upgrades that included implementing a new central plant to provide reliable heating and cooling performance for the next two to three decades. The uniquely designed central plant was completed without the need to demolish walls or the roof or interrupt the event schedule.

Upgrades also included new energy management systems and services that facilitate monitoring, analysis, alerts, reporting, tracking and data visualization of the convention center systems and building performance. These technology-based energy management services help the GWCCA facilities team assess building performance and work with Trane to modify systems as needed. The GWCCA team can use any web-connected mobile device to remotely access and adjust convention center building controls 24/7.

The project team also installed LED facility-wide lighting retrofits, installing lamps offering 500 percent longer life. The lighting improves illumination and color rendering and enhances visitors’ experience while ensuring the architectural integrity of the facility.

A measurement and verification service agreement will be implemented after the project upgrades are entirely completed this spring to help ensure that the building continues to operate and perform at optimal levels.

# # #


About Ingersoll Rand and Trane
Ingersoll Rand (NYSE:IR) advances the quality of life by creating comfortable, sustainable and efficient environments. Our people and our family of brands — including Club Car®, Ingersoll Rand®, Thermo King® and Trane® — work together to enhance the quality and comfort of air in homes and buildings; transport and protect food and perishables; and increase industrial productivity and efficiency. We are a $13 billion global business committed to a world of sustainable progress and enduring results. Trane solutions optimize indoor environments with a broad portfolio of energy efficient heating, ventilating and air conditioning systems, building and contracting services, parts support and advanced control. For more information, visit www.ingersollrand.com or www.trane.com.

About the Georgia World Congress Center Authority
Located in the heart of downtown Atlanta, the Georgia World Congress Center Authority (GWCCA) now includes Mercedes Benz Stadium, the 3.9 million-square-foot convention center, the 71,250-seat Georgia Dome, and 21-acre Centennial Olympic Park. Additionally, GWCCA manages operations of the Savannah International Trade & Convention Center.
These public facilities represent the largest combined convention, sports, and entertainment destination in the world. For more information, visit www.gwcca.org.

Photos and captions
Three options for exterior convention center photo: Rooftop pic
Building A Building B
Caption: Leaders from Trane and the Georgia World Congress Center Authority unveiled upgrades to the Atlanta convention center which are expected to cut energy costs and reduce the centers carbon footprint by 39 percent annually.
Photo courtesy of Georgia World Convention Center Authority

Image CMK-Trane
Caption: Shown here at the event held on Tuesday to unveil upgrades to the Georgia World Congress Center, which are expected to reduce energy use by more than a third, are (from left): Kevin White, general supervisor of engineering operations, Georgia World Congress Center Authority (GWCCA); Kevin Duvall, chief operating officer, and executive-in- charge of the upgrade project, GWCCA; Alan Word, project manager, Trane; Cameron Griffith, solutions advisor for Trane; Jeff Oden, operations project manager, GWCCA; Wayne Rosser,
physical plant manager, GWCCA; Jonathan Reeves, project manager, McKenney’s.